Version 18 and Integrated ILL Project PlanRevised March 6, 2008
New Server Preparation - completed
Re-indexing
- Re-index v. 17 keywords on production server – completed
- Full re-indexing next spring with implementation of new authorities functionality (re-indexing not required with v.18 upgrade)
Version 18 Data and Table Conversion and Testing
- First version 18 conversion – completed
- Second version 18 conversion – completed
- Third version 18 conversion – March 31 - April 2
- Final version 18 conversion – May 29 - June 1
- Test version 18 – November - May
Version 18 Information Sessions
- PALS prepares plan – completed
- Libraries register for sessions – completed
- Version 18 information sessions (online) – completed
- Q & A sessions – at User Group meetings in April and following the upgrade.
Integrated ILL
- First ILL conversion – completed
- Second ILL conversion – completed
- Third ILL conversion – April 3 - 4
- Final ILL conversion – May 31 - June 1
- Test ILL – December - May
- Training on Integrated ILL (in person and online) – April 17 - May 2
Planned “Go Live” Dates
- Version 18 – June 1
- Integrated ILL – June 1
Other Notable Dates
- Dev18 unavailable — March 31 - April 2
- Updated Version 18 client available to libraries – April 28
- Last day to update tables in version 17 – May 16
- Refresh data on lute (to be used for OPAC during down time) – May 22
- Last day to update tables and forms on dev18 – May 23
- Production server unavailable – May 29 (late in the day) - May 31
|